In time management, very important concepts for pmp exam preparation are the tools and techniques for sequencing activities.

Tools and Techniques for Sequencing Activities

A manager can apply any one of several sequencing tools to organize and schedule their activities.

- Precedence Diagramming Method (PDM)

This technique uses an illustrative approach to sequencing activities that uses boxes and rectangles to represent each activity. The visual representation helps a project manager to see and connect activities by precedence. The activities are studied typically to determine the logical relationship and are connected to each other by arrows, flowing from left to right. This technique helps to identify those activities that must happen before others can begin or finish. This type of analyzing is called Critical Path Methodology (CPM). There are many dependency relationship types to employ when using PDM. PMP exam prep must include PDM.

Finish-to-Start (FS) type is the most common dependency, which begins an activity only when the one before it is complete.

Finish-to-Finish (FF) type allows completion of one activity based on the completion of the activity before it.

Start-to-Start (SS) type starts an activity based on the initiation of the activity before it.

Start-to-Finish (SF) type allows completion of an activity only when the activity before is initiated. This is the most rarely used method.

- Dependency Determination

Dependencies are situations that affect the sequencing of activities due to circumstances both internal and external to the project. Typically, a project manager may encounter three types of dependencies. PMP exam prep should detail:

Mandatory dependencies

Discretionary dependencies

External dependencies

- Applying Leads and Lags

These are techniques used to either start or delay an activity based on its relationship with the previous activity or predecessor. Since dependency deals specifically with the beginning or ending of an activity, leads and lags are methods to start or delay an activity before the actual predecessor activity is started or finished. For example, you can have two activities scheduled as a Finish-to-Start type dependency. Applying a lead to this could result in having the successor activity begin five days before the finish of the predecessor activity. PMP exam prep should include examples of leads and lags.

- Schedule Network Templates

Using templates helps to make sequencing activities faster, efficient and consistent. These templates can be used to illustrate all the project activities or divided into a sub network or fragment network. PMP exam preparation should include examples of the templates.
Best Act Test Prep Book College Confidential Short Courses It's Never Too Late To Learn Something New Reasons Why Every College Society Needs Personalised Hoodies Examination in violation of potency (erectile dysfunction) Advantages Of Learning Martial Arts Guidelines For Learning Tae Kwon Do Top Rules For Selecting the Best College or University Learn It From Tiger Woods Golf Swing Searching For the Best College in a Planned Manner 5 Items You need to Learn about Getting rid of a Wisdom Tooth What are you going to learn in the BLS CLASSES? Learn about the connection between arteriosclerosis and heart attack Have your degree from the best of universities in US
print
www.yloan.com guest:  register | login | search IP(216.73.216.35) California / Anaheim Processed in 0.017366 second(s), 7 queries , Gzip enabled , discuz 5.5 through PHP 8.3.9 , debug code: 37 , 2946, 249,
Concepts for PMP Exam Preparation Anaheim