How To Install And Test The Running Of Jaw Crusher
The jaw crusher is equipment periodically by movable jaw approaching and leaving fixed jaw to broken the materials entered in crushing cavity
. It consists of base, movable jaw, main shaft, connecting rod, thrust plate, flywheel and motor.
How to install and test run the jaw crusher? Below are some suggestions.
1. Jaw crusher needs to be installed in a place sheltered from rain, do not place in the open.
2. The motor should be installed behind the jaw crusher, and the rotation direction must be done according to the requirement, and may not reverse.
3 Due to the vibration of jaw crusher is large at work so the machine should be installed on the concrete foundation. In order to reduce vibration, noise and influence towards the nearby building and structure, it shall place hardwood pad, rubber belt or other damping materials between crusher and concrete foundation. It should set aside discharge trough on foundation. The discharge trough should be laid a layer of metal plate and have enough angle of inclination, to avoid blocking the successful education of broken product.
4. The size of discharge opening should be adjusted according to the product particle size.
When adjust, it should loosen the T bolts and taut spring firstly. Use bolts from the top prop the adjust base, insert or take out some corresponding gaskets, then return the bolts from the top, the adjust base under the action of weight press to frame ear seat, at the same time press the gaskets group on together.
5. The coordination and management between jaw crusher and other equipments should be in favor of the assembly line working, ensure the working face without congestion.
6. In order to make the transportation of raw material and finished product convenient, it is better to use the mechanization transportation equipment for feeding and discharging materials.
7. Before commissioning, tighten the screws up and connecting parts, check the lubrication conditions.
8. Firstly using human power move the pulley to confirm the running is unimpeded. Then do the test without loading. In two hours it must not have impact, noise, seal leakage and pulley swing and shafts loose etc.. Temperature rise of Bearing should not more than 35 degrees, if discover any problems it must immediately stop the machine and do inspection.
9. Users should test the jaw crusher with load by 10 hours and adopted second hard ore. If there is no above problem and the temperature rise of bearing is not more than 70 degrees, then it can be put into production.
by: jocelyn
Wasps And Bees In Florida Suits For Tall And Large Men Profile And Performance Of Stone Production Line Perfect The Balance Between Seo And Web Designing Function And Metabolism Of Biotin Ltc Tour Europe Enjoy The Adventures And Historical Monuments 4 Ways Towards Recovery: End Withdrawal Signs And Symptoms At Home Today An Eastpointe Dentist Is There To Offer Its Very Best With Respect Of Health And Dental Care Spice Up Your Home With Modern Dining Tables And Other Tables Have Benefit Of Industrial Painting Services And Maximize Your Productivity Different Advantages Of Human Hair Wigs And Synthetic Wigs Use A Better And Innovative Way Of Making Tea By Tea Bags Reading And Its Attractions
www.yloan.com
guest:
register
|
login
|
search
IP(216.73.216.231) California / Anaheim
Processed in 0.017392 second(s), 7 queries
,
Gzip enabled
, discuz 5.5 through PHP 8.3.9 ,
debug code: 24 , 2667, 60,