subject: Installation And Commissioning Of Pebble Sand Maker [print this page] Installation of pebble sand maker: Installation of pebble sand maker:
1. Pebble sand maker is installed on concrete or steel structure on the basis of the foundation should be able to withstand four times the machine weight.
2, with broken airport different - installed in the plant operation or installed in the open-air operations. Should be installed crusher leveling so that the spindle and horizontal vertical.
3.River pebbles above the sand making machine should be set to the lifting equipment,lifting equipment capability according to the weight of the crusher, lifting space should be left in the river gravel above the sand making machine, to stay in the river gravel, sand making machine side of the appropriate space toprepared overhaul.
Commissioning of pebble sand maker:
River gravel, sand making machine in the factory, the factory has eight small space-timeload operation, the ministries is normal, however, in the river gravel, sand making machine on-site installation in place, should continue to conduct a comprehensive inspection.
1, Check the oil pipe is connected securely, commissioning should be re-added once the oil.
2, check all components connected, should be solid and reliable, carefully check the impeller on a foreign body, if any should be immediately removed.
3, check the motor wiring is correct, the normal voltage (380V 5%).
4.Before installing the belt, first start the motor rotation with the sand making machine signage direction (ie from the feed port and the impeller counterclockwise rotation) if it is contrary to the signs direction to adjust the motor wiring to make it spin to consistent with the signs direction, never allow the rotation in the opposite direction.
5, dual-motor-driven spindle assembly, with both sides of the motor, respectively, with the same number of triangular tape and spindle assembly is connected to both sides of the triangle belt tensioning should be adjusted the same, and straight. After the check, prior to the transfer of production, first empty the load and load test, the test to confirm there is no problem and then the transfer of production.