subject: North Water Transfer Project Was Delayed Five Years Multiple Factors Trapped [print this page]


Like and North Water Transfer Project, Transfer Project is not immune from the fate of being delayed for five years.

Seven years ago, on Dec. 27, North Water Transfer Project under construction, in accordance with the original plan, the east line of the end of 2007 through the water. May be limited by multiple factors such as pollution, the core of the Shandong provincial government recently heard news that Water Project in 2013 to achieve the water, to when the main water supply to the Jiaodong and the North of Shandong Province, and to have to Tianjin to provide emergency water supply conditions.

Jining, Shandong Environmental Protection Bureau Director of the Center Guang Yong propaganda that "Eastern was delayed mainly due to pollution, while Shandong effort to play 'rule, use, protection' of the water pollution control measures, but there are many contradictions, Situation is still grim. "

As a "success or failure in pollution control, difficulty in Shandong," the North Water Transfer Project, Water Pollution Control Yiru high on the environmental protection department head of Shandong sword of Damocles.

Bleak water North Water Transfer Project in Shandong points North and South, East and West two water lines, length 1191 km, 487 km long north-south route east-west route length 704 km.

Water in these lines, the distribution of their number was not the paper, chemical, coal, and pharmaceutical companies, only Jining City, the "Eleventh Five-Year" has been out of the city's total high energy consumption, heavy pollution enterprises 351, vetoed 223 items of new pollution.

Now, with 197.9 km trunk lines of Jining City, focusing on pollution control project is progressing well, included in the state, "North Water Transfer Project in Shandong pollution control unit for the implementation of the program" The 119 projects have been completed and 100 , 84% completed.

To implement the State Council's "After the first water diversion, First Stages of water, after the first green water" principle, the city's seven cities and counties in its jurisdiction, planning investment 429 million yuan of 7 Interception and diversion projects are under construction.

However, the situation is still not optimistic face. Guang-Yong told reporters, "At present a number of comprehensive measures to protect water quality have not yet fully in place, the city's low rate of the river section water quality standards. Water quality requirements for water quality are still far away from the diversion."

Reporter learned that, Jining City, only the Nansi Lake and the lower lake superior lake district basically reach the national Grade III standard, the city's water quality control sections of other rivers in the four or five levels, and the North Water Transfer There are a lot of difference compared to water quality standards. A similar situation also

South Taian. "Dawen, Light House River, Dongping Lake and other major rivers and lakes have not yet reached the standard functional areas, 80% of the water quality section is still subject to different levels of pollution, especially in the dry season surface water compliance rate lower." Taian EPA Public Information Section The chief said Osamu SUN.

New pollution problems North Water Transfer Project is still struggling with environmental problems.

It is understood Interception and diversion projects because the state approved a late interception in Jining City, 7 Diversion Project started construction before the end of 2008, is expected to "during" difficult to completed construction, play rule pollution benefits. 13 municipal sewage treatment plant water reuse project has been completed five, but only in the water reuse project in Zoucheng played a part of the benefit.

Again in Tai'an City, although the city closed the Taishan cement plant, sea-based chemical company Kuixing, but "many of the current established in the city sewage treatment plant operator was not ideal, pipe network lag, load operation low, low and excessive sewage influent water quality problems occur. "

SUN repair that is the main pollutant emissions over the carrying capacity of the environment, and with the rapid economic development, pollutant generation and a corresponding increase in emissions, emissions reduction is very difficult.

North Water Transfer Project Was Delayed Five Years Multiple Factors Trapped