Grinding Mill have Raymond mill, High pressure suspension mill roller , high pressure micro powder mill , Super pressure trapezium mill and three-ring medium speed milling machines , investment and production based on actual customer to choose their own mill type , but is worth noting that Note in the mill operation , the equally important mill users to note.

Starting mill , should check whether all the access door closed tight , adjust the fan and spindle turn , exhaust valve in the fully open position should be . After starting the host should immediately feeding ( should add a small pellet , together with normal Liaodu material ) and open air flow valve in the inlet is not out to ensure the premise should be dusting off a small exhaust valve . Then align the product fineness . With a broken jaw and improve machine should be checked before start of the jaw plate crusher feed size whether gap size adjustment of machine speed should be up to approximate product size requirements . Finally start the following order :

1 , open bucket elevator

2 , starting Jaw Crusher

3, there are materials to be silos , the start of machine

4, start the blower ( air load starts to be loaded after the normal operation )

5 , start the host , the host at the start instant starts electromagnetic vibrating feeder . Milling work shall be started at this time . Simple sequence of operations , said the following: " start " Crusher Hoist === === === fan of the host machine === === feeder .

Shutdown the machine should be shut down following order :

1 , first turn off the feeder stopped feeding

2 , for one minute after the host

3, the net residual material after blowing stop blower

4 , the final closing of machine

Shutdown sequence is : Feeder Blower === === === analysis of the host machine

Note : hoist transport of materials to silos must end, then stop the first stop crusher upgrade , this should be feeding quantity and changes in storage .

5MillNot allowed to work freely in the normal fuel , to ensure safety, Grinder in any part of the unusual noise, or sudden load increase should immediately stop inspection , troubleshooting , in order to avoid a major accident . Continue the boot must be removed excess material within the mill , has just opened when the current machine is too large , of the startup .