Installation And Commissioning Of Pebble Sand Maker
Installation of pebble sand maker:
Installation of pebble sand maker:
1. Pebble sand maker is installed on concrete or steel structure on the basis of the foundation should be able to withstand four times the machine weight.
2, with broken airport different - installed in the plant operation or installed in the open-air operations. Should be installed crusher leveling so that the spindle and horizontal vertical.
3.River pebbles above the
sand making machine should be set to the lifting equipment,lifting equipment capability according to the weight of the crusher, lifting space should be left in the river gravel above the sand making machine, to stay in the river gravel, sand making machine side of the appropriate space toprepared overhaul.
Commissioning of pebble sand maker:
River gravel, sand making machine in the factory, the factory has eight small space-timeload operation, the ministries is normal, however, in the river gravel, sand making machine on-site installation in place, should continue to conduct a comprehensive inspection.
1, Check the oil pipe is connected securely, commissioning should be re-added once the oil.
2, check all components connected, should be solid and reliable, carefully check the impeller on a foreign body, if any should be immediately removed.
3, check the motor wiring is correct, the normal voltage (380V 5%).
4.Before installing the belt, first start the motor rotation with the sand making machine signage direction (ie from the feed port and the impeller counterclockwise rotation) if it is contrary to the signs direction to adjust the motor wiring to make it spin to consistent with the signs direction, never allow the rotation in the opposite direction.
5, dual-motor-driven spindle assembly, with both sides of the motor, respectively, with the same number of triangular tape and spindle assembly is connected to both sides of the triangle belt tensioning should be adjusted the same, and straight. After the check, prior to the transfer of production, first empty the load and load test, the test to confirm there is no problem and then the transfer of production.
With its high quality products such as
Iron ore concentratorRaw material millClinker rotary kilnHenan Hongxing mining machinery Co.Ltd has ascended in the front rank of the world in the exporting of mining equipments.
by: hxjqchina
Principle And Drive Mechanism Of Cone Crusher Search Engine Optimisation Made Easy. Beneficial Tips And Tricks! On The Maintenance And Upkeep Of The Mill Buy Alli Now And Stop Excess Fat Find A Decent Book On Relationships And Break Ups Healthy And Balanced Eating Can Be Enjoyable And Simple Catering Services In Farnham, Alton And Fleet Practical Ways To Make Money Online Quickly And Easily Meridian Ent Makes Appointment Requesting Easy And Convenient Central Air Conditioners And You Report Shoes And Seychelles Shoes For The Trendy And Independent Woman Fiberglass Wrought Iron Door-an Improved Sense Of Security And Style Carpet Cleaning Croydon And Carpet Cleaning Wimbledon Offered By Direct Cleaners Team
www.yloan.com
guest:
register
|
login
|
search
IP(216.73.216.125) California / Anaheim
Processed in 0.017039 second(s), 7 queries
,
Gzip enabled
, discuz 5.5 through PHP 8.3.9 ,
debug code: 25 , 2944, 60,